dc.contributor |
Universidade Federal de Santa Catarina. |
pt_BR |
dc.contributor.advisor |
Marchiori, Fernanda Fernandes |
|
dc.contributor.author |
Vieira, Mariana Aparecida |
|
dc.date.accessioned |
2022-12-20T13:41:42Z |
|
dc.date.available |
2022-12-20T13:41:42Z |
|
dc.date.issued |
2022-12-09 |
|
dc.identifier.uri |
https://repositorio.ufsc.br/handle/123456789/243162 |
|
dc.description |
TCC (graduação) - Universidade Federal de Santa Catarina, Centro Tecnológico, Engenharia Civil. |
pt_BR |
dc.description.abstract |
A indústria da construção civil apresenta fluxos complexos, com uma grande quantidade de
atividades, tornando o planejamento de seus empreendimentos um processo trabalhoso e de
difícil compreensão pelos usuários. Para que esse cenário seja melhorado, a indústria precisa
atribuir inovações tecnológicas que facilitem a visualização do cronograma. O planejamento
4D tem se mostrado eficiente nesta tarefa, através da interação do cronograma de obras com a
modelagem 3D, com capacidade de simular a construção e identificar erros do planejamento.
No entanto, por ser uma tecnologia ainda nova apresenta desafios quanto a falta de padrão de
visualização e de detalhamento. A pesquisa busca contribuir para a padronização da elaboração
do BIM 4D para um planejamento de curto prazo. O método de pesquisa adotado foi o de estudo
de caso com acompanhamento semanal de uma obra residencial e comercial de médio padrão
em concreto armado, onde foi realizado o estudo visual do modelo 3D disponibilizado e a
comparação do BIM 4D teórico e real. Como resultado foi possível identificar o quanto o
modelo virtual pode ser benéfico para evitar problemas durante a construção, como a simulação
de cenários antes mesmo do empreendimento ser executado, e as dificuldades quanto ao
desenvolvimento do modelo para um planejamento de curto prazo, como a falta de
detalhamento do modelo 3D necessitando acrescentar novos elementos. |
pt_BR |
dc.description.abstract |
The civil construction industry has complex flows, with a large number of activities, making
the planning of its projects a laborious process and difficult for users to understand. For this
scenario to be improved, the industry needs to adopt technological innovations that facilitate
the visualization of the schedule. 4D planning has proven to be efficient in this task, through
the interaction of the construction schedule with 3D modeling, with the ability to simulate
construction and identify planning errors. However, as it is still a new technology, it presents
challenges regarding the lack of visualization and detailing standards. The research seeks to
contribute to the standardization of the development of BIM 4D for short-term planning. The
research method adopted was the case study with weekly follow-up of a mixed use redident ial
and comercial building, made of reinforced concrete, where the visual study of the 3D model
available and the comparison of the theoretical and real 4D BIM was carried out. As a result, it
was possible to identify how much the virtual model can be beneficial to avoid problems during
construction, such as the simulation of scenarios even before the project is executed, and the
difficulties regarding the development of the model for short-term planning, such as lack of
detailing of the 3D model needing to add new elements. |
pt_BR |
dc.format.extent |
108 |
pt_BR |
dc.language.iso |
por |
pt_BR |
dc.publisher |
Florianópolis, SC. |
pt_BR |
dc.rights |
Open Access. |
en |
dc.subject |
Planejamento 4D |
pt_BR |
dc.subject |
Modelagem |
pt_BR |
dc.subject |
BIM |
pt_BR |
dc.subject |
Planejamento de obras |
pt_BR |
dc.title |
Modelagem 3D para padronização do BIM 4D de um empreendimento residencial-comercial |
pt_BR |
dc.type |
TCCgrad |